The operational test teams identified deficiencies that required software modifications and additional time and resources which caused delays in Block. 4
8 août 2017 However DOD does not plan to make the F-35 Block 4 a separate MDAP. Instead
25 avr. 2022 F-35 Aircraft Variant. 20. Figure 9: On-Time F135 Engine Delivery Declined in 2021. 21. Figure 10: Change in Block 4 Cost Estimates from ...
Block 4 modernization will add new hardware software
“Block 4” is the title of the most current incremental software upgrade to the F-35 fighter as part of its Continuous Capability Development and Delivery
27 avr. 2022 DOD intends for Block 4 development efforts to upgrade F-35 hardware and software systems. Block 4 costs continued to rise during 2021 due to ...
18 mars 2021 GAO found the F-35 program office collects data on many Block 4 software development metrics a key practice from GAO's Agile Assessment ...
30 janv. 2020 The Block 4 VV&A plan must ensure accreditation of the JSE for use in operational testing during the 30R07/08 F-35 software release time frame.