Apply to Discharge A CTMP Condition
You need to apply to the Department of Planning and Place who will consult the Transport Planning Team.
To apply: 1. complete the pro-forma in full - use the guidance notes (in blue) on the form to help you 2. send the pro-forma with your completed application form Any questions that you feel do not apply to your development should be marked N/A.
T.
,
Approval Process
It can take up to eight weeks to approve a CTMP.
This depends on the: 1. quality of your initial submission 2. complexity of your project If you do not submit the CTMP using the correct pro-forma, the approval process will be delayed.
Your application could be returned and you may have to resubmit it in the correct format.
The Department of Plannin.
,
Construction Traffic Management Plans
If you applied for planning permission for your development and a condition of the planning consent was a CTMP, it needs to be formally discharged before you can start work on site.
If you start work before the CTMP is discharged, we could take enforcement action.
,
Red Routes
If your development is on or adjacent to the Transport for London Road Network (red route), you will also need to liaise with Transport for London (TfL).
TfL can issue licences you need, including scaffold licences.