PMP Formulae & Tips Cheat Sheet |
Important Formulas for the PMP® exam
Important Formulas for the PMP® exam Page 2 Earned Value Formulas SV = EV-PV CV = EV-AC SPI = EV/PV CPI = EV/AC Forecasting EAC • EAC = BAC / cumulative CPI - when ETC work i e remaining work is predicted to be performed at the cumulative CPI This assumes the to date CPI will continue in future |
How is BAC used in project management?
This final BAC could then be used to better inform resource allocation, and gauge project performance throughout the life of the project. You can see how BAC is used in association with the earned value formula to understand how a project is tracking from a cost and schedule basis here.
How BAC helps in earned value calculation?
BAC helps in earned value calculation. For example, let us say the BAC is 100,000 USD, and 25% work has been completed, meaning the planned value is 25,000 USD. Let’s say you want to construct a house. The breakdown of the cost for this project will be as follows:
What does BAC & CPI mean?
That's Estimate at Completion and it works out the expected final and total cost of the project, based on project performance. (BAC = budget at completion. CPI = cost performance index)
Budget at Completion Formula PMP® Exam Topic
One of the critical concepts within the Earned Value area of formal project management is Budget at Completion (BAC). The Project Management Institute (PMI)’s Project Management Professional (PMP)® certification exam may include questions about, or driven by, the earned value (EV) performance calculations, including BAC. The great news is there is
Determine Budget at Completion
The PMI’s A Guide to Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, includes control cost processes enabling forecasting of the project’s completion from a budgetary lens. The PMBOK® Guide gives this definition of BAC: “the sum of all budgets established for the work to be performed.” At the most basic level for example, if th
Analogous Estimation
An analogy is where you take one idea to explain or clarify something similar. The comparison of like things to find meaning, or in the project management context, budget, can be forecasted as an analogous estimation. The BAC technique of analogous estimates can help with projects in which there is limited information for the current workif the pro
Expert Judgement
Project managers looking to establish a BAC will sometimes depend on the input of experts to determine the budget at completion. This BAC technique is known as “expert judgment.” The expertise of the subject matter expert can be based on the “training or educational background, career experience, or knowledge of the product/market.” When using Expe
Parametric Estimation
The BAC definition encompasses the “Parametric estimation” technique. For estimates of budget, cost, and project duration, the project manager will “break down the project into sub-components and match them with the appropriate equation to obtain the estimates.” Consider this example from plainsware.comof a parametric estimate for budget at complet
Pros and Cons of Bac Analysis
Those who hold the PMP® certification may look to the PMI’s resource library for insights on the BAC definition and formula. As a budget tool, the BAC is simply: “the amount of resources estimated as necessary to complete the work described in the scope statement.” projectmanagementacademy.net
How Bac Fits Into Earned Value and PMP® Certification Exam
Project Managers should not simply search the term “BAC PMP” to prepare for the PMP certification exam. Instead, know BAC questions are likely to be about the BAC techniques and how BAC fits into the larger earned value practice. In the provided Earned Value Terminology chart, BAC is highlighted for easy reference. As part of the PMP certification
Conclusion
The Budget at Completion (BAC) is part of the Earned Value (EV) terms and formulas used by Project Managers Professionals (PMP) to manage the cost process. Although BAC does not have a formula, the BAC is needed to complete many EV formulas. Project Managers must use their own knowledge to determine which BAC technique to use for a project. Answers
![All the PMP Formulas and Calculations All the PMP Formulas and Calculations](https://pdfprof.com/FR-Documents-PDF/Bigimages/OVP.uS3UHBFj1oT8jzgc2fenGgHgFo/image.png)
All the PMP Formulas and Calculations
![PMP Formula Cheat Sheet PMP Formula Cheat Sheet](https://pdfprof.com/FR-Documents-PDF/Bigimages/OVP.seNDzlUIdEup9fU3o3w-tAHgFo/image.png)
PMP Formula Cheat Sheet
![How to Memorize PMP Exam Formulas in Under 10 mins How to Memorize PMP Exam Formulas in Under 10 mins](https://pdfprof.com/FR-Documents-PDF/Bigimages/OVP.UyPBqC7cfvYSboHev4X4cgHgFo/image.png)
How to Memorize PMP Exam Formulas in Under 10 mins
PMP Exam Formulas Summary
PMP Exam Formulas Summary. Earned Value Management. Name. Abbr. Formula. Note. Budget At Completion BAC. BAC = Total budget. What the project budget is. |
Sample PMP Earned Value Questions Given a project with the
What formula might you use for BAC? A. [(BAC – EV) / (CPI * SPI)] + AC. B. new bottom-up estimate. C. |
PMP Formulas mentioned in the
by Edward Chung PMP (http://edward-designer.com/web/pmp/) BAC = Budget at completion ... Formula. Interpretation. Estimate at. Completion (EAC) if. |
PMP Formulas & Exam Tips- Cheat Sheet www.ecostarplan.com
What level of performance. Index (Based on BAC & EAC) must future project meet in order to meet the project's cost based on past performance (EAC)?. |
Important Formulas for the PMP® exam
EAC = AC + [(BAC – EV) / (cumulative CPI x cumulative SPI) – when both cost and schedule performance indices are considered for performing remaining work. Most |
PMP Quick Reference Guide for Math Formulas
BAC includes contingency reserves for activities and defines how much money will be spent during project in total. • Estimate to Complete (ETC). ETC can be |
This EVMS Training Snippet sponsored by the Office of Acquisition
These reports are useful for anyone responsible for project management. should not be developed solely based on EAC formulas referred to as IEACs. |
Pmp-Formula-Pocket-Guide.pdf
Please see disclaimer on the PMP Formula Study Guide. © 2008 ScopeCreep Project Management Consultants. EAC 'typical' = AC + ((BAC - EV) / CPI). |
Earned Value Management Tutorial Module 6: Metrics Performance
The second EAC formula is as follows: EAC = AC/EV x BAC. This calculation uses the Actual cost Earned value and Budget at Completion for the project. |
Project Management 5e
PCIB = EV/BAC. ? It is based on the original budget estimates. ? PCIC = AC/EAC. ? It is based on the actual costs and the estimated cost at completion. |
PMP Exam Formulas Summary
bbr Formula Note Budget At Completion BAC BAC = Total budget What the project budget is |
Important Formulas for the PMP® exam - Pmguruonline
C + [(BAC – EV) / (cumulative CPI x cumulative SPI) – when both cost and schedule performance |
Mastering the PMP® Calculations
C PV SPI CPI BETC The arrows show the formulas that are needed by the target formula |
PMP Formulas & Exam Tips- Cheat Sheet wwwecostarplan
mulas Exam Tips- Cheat Sheet Total Float / Slack (There is a start formula BAC Budget At Completion How much did we BUDGET for the TOTAL project effort? CV |
PMP Quick Reference Guide for Math Formulas - Master of
determined during cost management activities, in Determine Budget Process, in a project BAC |
5th Edition PMP/CAPM FORMULA SHEET (from Media Center
(P +4R + O) ÷ 6 (3-Pt Est ) Std Dev PERT = (P – O) ÷ 6 BAC = Σ of Budgeted Costs AC = Σ of |
The Formula Table Explained Exponentiation
r of formulas needed on the PMP® Exam require exponentiation The exponent is usually shown as a budget (BAC - EV) modified by both cost performance and schedule |
PMP Formulas mentioned in the - Edward Chung
ains the same Formula Interpretation Estimate at Completion (EAC) if CPI remains the |
Earned Value Formulae - Mosaic Projects
on the set numbers that can be included in a PMP question, EAC#1 and EAC#2 are the same Substituting this formula for AC in the equation EAC#2, where EAC = AC + |