coned gas demand response program
Does Con Edison have a natural gas demand response pilot program?
In August 2018, the New York Public Service Commission approved a petition by Consolidated Edison Company of New York, Inc. (Con Edison) for a $5 million, three-year natural gas demand response pilot program, one of the first demand response projects for natural gas.
Does Con Edison have pipeline transport contracts?
Con Edison has firm pipeline transport contracts that enabled the company to meet 83% of its peak-day demand in the winter of 2017–2018. Firm contracts provide Con Edison with an agreed-upon supply of natural gas that cannot be curtailed except under unforeseeable circumstances.
What is a demand response program?
Demand response (DR) programs help manage utility usage during periods of peak demand. These programs have become fairly common in the electricity sector during the past 10 to 15 years. For the electric power sector in the United States, peak electricity demand occurs in the summer, when warm weather increases the demand for air conditioning.
Program Overview
In 2013, DCAS launched the City's Demand Response (DR) Program to provide city agencies with the ability to earn revenue by reducing their energy usage during periods of peak usage. As part of the energy industry’s increasing use of pricing incentives to add flexibility to energy delivery systems, the revenue from the DR Program is paid by utility
Outcomes
From 2013-2021, City agencies earned total program revenues of more than $100 million. In Summer 2021, 517 facilities across 31 agencies and organizations committed to reduce more than 103 MW of load during peak demand periods. That's the equivalent to removing almost 415 mid-size schools from the grid. See the City of New York's Demand Response pr
How to Participate
DCAS works with partner agency staff third-party vendor NuEnergen to identify City buildings that are suitable for DR. The facilities must have curtailable load and real-time meters with communication capabilities. In some instances, DCAS can work with the relevant utility to facilitate the necessary metering upgrades. Contact us to check if your f
Already enrolled?
Log in to the ENERTRAC web and mobile portalto track your agency's Demand Response participation and set customized user alerts. Download the ENERTRAC User Guide nyc.gov
Con Edison Performance-Based Gas Demand Response Pilot
Aug 6 2021 Disclaimer: On April 26 |
2020 Demand Response Forum - Con Edison
Feb 18 2020 Competitive Procurement Plan. • Rider R Participation. • Gas Demand Response Pilot. • Residential Demand Response Program (BYOT). |
Gas Demand Response Report on Pilot Performance – 2019/2020
Jul 1 2020 8 The Con Edison gas supply portfolio is designed to meet the needs of its ... for Natural Gas Customers Program |
Gas Demand Response Pilot Implementation Plan 2021-2022
Jul 1 2021 Consolidated Edison Company of New York |
Gas Demand Response Program Application
Aggregators and Direct Participants must submit a pilot application as evidence of intent to provide Load. Relief in accordance with Con Edison's Demand |
Three Utility Approaches to Gas Demand Response
Nov 14 2018 Objective: Incentivize customers to reduce natural gas demand ... •Demand Response developed as a support tool in response to on-going. |
Residential Natural Gas Demand Response Potential during |
Gas Long-Range Plan - Con Edison
The Consolidated Edison Company of New York Inc. (CECONY) operates a gas energy efficiency |
Commercial Demand Response (Rider T) Program Guidelines
Feb 28 2022 Disclaimer: This document contains only guidelines for the Con Edison Demand Response. (DR) programs. The Con Edison Electric Tariff ... |
Non-Pipeline Solutions to Provide Peak Period Natural Gas System
Jan 31 2020 Con Edison expects that each Response to this RFI should at a minimum provide a plan for a potential supply-side alternative to pipeline ... |
Gas Demand Response Pilot Guidelines - Con Edison
21 juil 2020 · Customer – Any firm gas customer taking service from Con Edison Demand Response (DR) – Load Relief upon request Direct Participant – A |
Gas Demand Response Implementation Plan - Con Edison
1 juil 2020 · (“Con Edison” or “the Company”) proposed the Smart Solutions for Natural Gas Customers Program (“Smart Solutions”)1 to address increased |
Demand Response for Natural Gas Distribution - The Brattle Group
Natural gas demand response (“Gas DR”) could be a part of the solution, but has been ConEd proposed a natural gas DR program for firm customers (C&I are |
Three Utility Approaches to Gas Demand Response
14 nov 2018 · For covers, the three pictures should be the same size and in a straight line Rhode Island – EE program (5-10 sites for 50 DTh/hr reduction) □ |
IPKeys Demand Response Program - IPKeys Power Partners
IPKeys Demand Response Program greenhouse gas emissions, accelerate MegaWatt (MW) – DLRP CSRP Rates vary by location on ConEd's network |
Con Edisons Targeted Demand Side Management Program - ACEEE
Con Edison's Targeted Demand Side Management Program: Replacing Distribution Replace electric air conditioning with gas or steam air conditioning |