fidic 1987 2011
Owing to the continuing demand for the Fourth Edition 1987 of the FIDIC. Conditions of Contract for Works of Civil Engineering Construction reprinted in 1992
02.-FIDIC-Red-Book-4th-edition.pdf
© FIDIC 1987. I. Page 4. 16.1. Contractor's Employees. 8. 16.2 Engineer at Liberty to Object. 8. 17.1 Setting-out. 9. 18.1 Boreholes and Exploratory Excavation.
Contractors Claims Under The FIDIC Contracts For Major Works
17-Mar-2005 a claim for additional payment [see Sub-Clause 20.1 last sentence]. On the other hand
24 CLAUSE 20 DISPUTE RESOLUTION.pdf
1987 Red Book to amend Clause 67 to replace the Engineer's Decision with a ... In 1996
international federation of consulting engineers (fidic)s general
The Red Book: the Conditions of Contract for the implementation of civil engineering works contracts the fourth edition of 1987 which has been re-printed in
FIDIC Sub-Clause 3.5 [Determinations] Explained Introduction FIDIC
Although the. Engineer had been required to carry out consultations with both Parties and determinations under various clauses of the 1987 Red Book there was
An Engineers / Dispute Adjudication Boards Decision Is
under Clause 67 of the FIDIC Conditions of Contract for Works of Civil Engineering. Construction (the “FIDIC Conditions” or. “Red Book”) fourth edition
FIDIC AND DISPUTE ADJUDICATION BOARDS (DAB(s))
18-Mar-2015 contract for civil engineering works – the “Red Book” – in 1957 it was based on ... ▫ Under FIDIC construction contracts from 1957 until 1987
Fidic 1987 red book pdf
Fidic 1987 red book download pdf. Academia.edu uses cookies to personalize content tailor ads and improve the user experience. By using our site
Untitled
Contractor's Equipment Temporary Works and Materials; Exclusive. Use for the Works. 54.2 Employer not Liable for Damage. 54.3 Customs Clearance. © FIDIC 1987.
fidic 1987 2011
Owing to the continuing demand for the Fourth Edition 1987 of the FIDIC. Conditions of Contract for Works of Civil Engineering Construction reprinted in 1992
Untitled
Copies of the FIDIC Conditions of Contract can be obtained from. Switzerland FOURTH EDITION 1987 ... suitable for use on domestic contracts.
Arabic Translation of FlDlC
of the FIDIC contract: Conditions. o f Contract f o r Works o f C i v i l. Engineering Construction. (hereinafter the "Red Book"). The.
Contractors Claims Under The FIDIC Contracts For Major Works
???/???/???? a claim for additional payment [see Sub-Clause 20.1 last sentence]. On the other hand
Payments Measurements
https://justice-academy.com/wp-content/uploads/2020/09/Payments-Measurements-Adjstments-of-CP-5.pdf
Variations Claims & Compensations (Red Books)
FIDIC Red Book 1987 1999 & 2017 1.2 Variations under FIDIC 1987 4th edition ... Sub-clause 52.1 of the FIDIC red book 4th edition states:.
CLAUSE 20 DISPUTE RESOLUTION
%20DISPUTE%20RESOLUTION.pdf
Overview of the Red Books of FIDIC Conditions of Contracts
Red Book and 1987 Yellow book. – The FIDIC 1999 suite was published in 1999 which constitutes of the Short Form (Green) Construction (Red)
Introduction to FIDIC Conditions of Contracts (Red Books)
Introduction to FIDIC Conditions of. Contracts (Red Books). Lecture # 02. 08th August 2020. Author-presenter: Tahseen Saleh. FIDIC Red Book 1987
FIDIC Contract Forms and the new MDB Contrcat C. Wade
https://fidic.org/sites/default/files/wade_oct05.pdf
FIDIC Red Books{1987, 1999 & 2017}
Justice Academy
Introduction to FIDIC Conditions of
Contracts (Red Books)
Lecture # 02
08thAugust 2020
Author-presenter:Tahseen Saleh
FIDIC Red Book1987, 1999 & 2017
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© Tahseen -2019
1Tahseen Saleh
Outline
1.About FIDIC
2.Background of FIDIC Contracts
3.FIDIC Contract Documents
Introduction to FIDIC Conditions of Contracts (Red Books)FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© Tahseen -2019
2Tahseen Saleh
Section 1
1.About FIDIC
2.Background of FIDIC Contracts
3.FIDIC Contract Documents
Introduction to FIDIC Conditions of Contracts (Red Books)FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© Tahseen -2019
3Tahseen Saleh
FIDIC is the abbreviation of the ͞Fédération stands for :(The International Federationof ConsultingEngineers)
The FIDIC wasestablishedin 1913
Promotesand implementsthe consulting engineering
industry'sstrategicgoalsMembersendorseFIDIC'sstatutesand policystatements
and complywithFIDIC'sCode of Ethics.Developsand promotesbusiness practice: Business
Integritymanagement; Project Sustainability
management;Qualitymanagement; RiskManagement1-About FIDIC
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© Tahseen -2019
4Tahseen Saleh
The FIDIC Organizes:
Extensive programs of seminars and conferences
International Training Programs (courses & workshops) Capacity Development programs (accredited trainers, training suppliers, programs and events)The FIDIC Publishes:
Business practice guides
Professional services agreements and guides
Works Contracts and Guides
1-About FIDIC
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© Tahseen -2019
5Tahseen Saleh
Groups of Member Associations
GAMA: FIDIC Group of African Member Associations
ASPEC: FIDIC Asia-Pacific Member Associations
EFCA: European Federation of Engineering Consultancy Associations FEPAC: PanamericanFederation of Consultants / FedaraciónPanamericana1-About FIDIC
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© Tahseen -2019
6Tahseen Saleh
General Assembly
2-6 delegates per Member Association
Executive Committee
9 elected members including President, Vice President, Treasures
President: Alain Bentejac(France)
MoncifZiani(Morocco) Member (finished last September)Aisha Nadar (initially Egyptian
Secretariat
8-9 staff including managing Director & General Manager
Committees
Assessment Panel For Adjudicators (APA)
Business Practice Committee (BPC)
Capacity Building Committee (CBC)
Contracts Committee (CC)
Integrity Management Committee (IMC)
Membership Committee (MemC)
Risk and Quality Committee (RC)
Sustainable Development Committee (SDC)
1-About FIDIC
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© Tahseen -2019
7Tahseen Saleh
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
8Tahseen Saleh
1-About FIDIC
With FIDIC president & Ex-presidents
Strategy 1 Consultant selection (QBS)
Client (Employer) selects the consultant
on the basis of:Professional competence and experience
Managerial ability
Availability of resource
Professional independence
Appropriate risk management
Integrity Management System
Quality management System
Appropriate fees
1-About FIDIC
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
9Tahseen Saleh
Strategy 2 Standardized Procurement
They are:
More transitional partnerships
Shorter delivery time
New forms of contract
They are needed for:
Common recognition of obligations and
liabilitiesIncreased protection to clients
Increased competition
values1-About FIDIC
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
10Tahseen Saleh
Strategy 3 Innovation and Sustainability
Project sustainability management and
sustainability management guidelinesEnvironmental Management Systems
1-About FIDIC
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
11Tahseen Saleh
Strategy 4 Risk Management
Risk management Manual (1stEdition
1997)Risk Management Primer
Professional Indemnity Insurance
Professional Liability Insurance
Insurance of Large Projects
Managing Risks
1-About FIDIC
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
12Tahseen Saleh
Standard Contracts and Agreements:
Construction (Red)
Plant and Design ʹBuild (Yellow)
EPC / turnkey Projects (Silver)
Short Form of Contract (Green)
Design, Build and Operate Projects (Gold
1-About FIDIC
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© Tahseen -2019
13Tahseen Saleh
New FIDIC Releases
Compared with 1999 releases
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© Tahseen -2019
14Tahseen Saleh
1-About FIDIC
FIDIC Releases
The Emerald Book -Conditions of Contract for
Underground Works
This Book was released in April 2019
Conditions of Subcontract for Plant and Design
(yellow book 1999) 1st Edition Dec. 2019FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹCOPYRIGHT 2019
15Tahseen Saleh
1-About FIDIC
The Latest Releases
Section 2
1.About FIDIC
2.Background of FIDIC Contracts
3.FIDIC Contract Documents
Introduction to FIDIC Conditions of Contracts (Red Books)FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© Tahseen -2019
16Tahseen Saleh
Background of FIDIC Contracts
The FIDIC Form of Contract
The Conditions of Contract (International) for Works of Civil Engineering Construction was published in August 1957. (Long title!). ͞
This was based on the ACE Form
This was popularly known as the ͞Red Book
2-Background of FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
17Tahseen Saleh
Background of FIDIC Contracts
The FIDIC Form of Contract 2ndEdition
The Second Edition was published in July 1969 after the document was approved and ratified by the International Federation of Asian and Western Pacific Contractors'Associations.
A supplementary section containing Conditions of Particular Application to Dredging Works was added as Part III.
A re-print of the Second Edition in 1973 added the approval and ratification by the Associated General Contractors of America and the Inter-American Federation of Construction Industry.
2-Background of FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
18Tahseen Saleh
Background of FIDIC Contracts
The FIDIC Form of Contract 3rdEdition
The publication of the ICE Fifth Edition in June 1973 which was controversial (arguable) provided an impetus or momentum for a further revision of theRed Book.
The Third Edition of the Red Book was published inMarch 1977 which incorporated some significant
changes. But these changes did not follow in respects the changes made in the ICE Fifth Edition.The Third Edition considered and avoided all the
principal difficulties in the ICE Fifth Edition2-Background of FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
19Tahseen Saleh
Background of FIDIC Contracts
The FIDIC Form of Contract 4thEdition
The Fourth Edition was published in September 1987 with major revisions made to the Third Edition.The Changes included the Title where the word ͞International͟was deleted, inviting parties from all over the world to use the Red Book not only for International contracts but also in domestic contracts.
In 1988, the Fourth Edition of the Red Book was reprinted with a number of editorial amendments which were identified at the end of the document. These amendments were very minor.
2-Background of FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
20Tahseen Saleh
Background of FIDIC Contracts
The FIDIC Form of Contract 4thEdition (Cont'd)
In 1992, further amendments to the Fourth Edition of the Red Book were introduced in the reprint of the document.Some of the amendments were directed towards a
more uniform style of drafting. Other amendments were of significant nature, either in adding to or changing the meaning of the relevant clauses of the Form.In November 1996, the FIDIC published a document
2-Background of FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
21Tahseen Saleh
Background of FIDIC Contracts
The 1996 Supplement to the FIDIC 4thEdition
It is intended to provide the use with alternative arrangements in three controversial areas of the Red Book, thus giving him a choice in the method to be used. These areas are: Settlement of Disputes, Payment and Preventing Delay in Certification for thePurpose of payments.
The Sections of the Supplement are entitled as follow;2-Background of FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
22Tahseen Saleh
Background of FIDIC Contracts
In 1995, the Orange book was published for Design-Build and TURNKEY projects.The 1995 Orange book reflected a move away from the FIDIC forms which had adopted the traditional role of the Engineer. Also, submission to the Engineer for his ͞Decision͟prior to pursuing a dispute was eliminated and the DAB was introduced.
In 1994 FIDIC established a task group to update the 1992 Red Book and 1987 Yellow book.The FIDIC 1999 suite was published in 1999 which constitutes of the Short Form (Green), Construction (Red), Plant and Design-Build (Yellow) and EPC/Turnkey (Silver).
FIDIC Conditions of Contract for Design, Build and Operate Projects (Gold) was published in 2008.2-Background of FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
23Tahseen Saleh
Section 3
1.About FIDIC
2.Background of FIDIC Contracts
3.FIDIC Contract Documents
1.Current FIDICContracts
2.StructureofFIDICContracts
3.Which Form to Use
Introduction to FIDIC Conditions of Contracts (Red Books)FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© Tahseen -2019
24Tahseen Saleh
3 FIDICContract Documents
3.1Current FIDIC Contracts
3-FIDIC Contract Documents
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
25Tahseen Saleh
FIDIC Short Form
The Green Book
Short Form of Contract
1stEdition 1999
Short sentences; simple straight forward language.15 Clauses in 10 pages
The complexities of other forms is not present
Suitable when work is not complicated.
For building or engineering worksof relative smallcapital value and/or short construction period. (Projectsup to US $ 500,000 and duration not more than6 months)
3.1 Current FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
26Tahseen Saleh
FIDIC Short Form
May also be suitable for contracts of greater value, if relatively simple or repetitive work. Can be suitable for certain larger construction projects and for longer construction period. Regularly used in some suitable cases for contracts with value up to US$10,000,000. The upper sum me be ignored in simple repetitive work.Limiting the duration of the construction period to that time when the contract sum can remain fixed, i.e. without allowance for escalation and other changes in costs (usually contractors agree to keep their prices firm for up to 12months, or sometimes more than that).
3.1 Current FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
27Tahseen Saleh
FIDIC Short Form
Under the usual arrangements of this type of contract:The Employer Provides the finance.
Works comprise construction but may include, or wholly comprise electrical, mechanical or other works. Design can be provided by the Employer, the EmployerRepresentative (if any) or by the Contractor.
Employer may wish to order variations to the Works. Employer may wish to appoint an individual or a firm, as his Representative, to carry out certain duties.Employer has choices for evaluation and payment.
3.1 Current FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
28Tahseen Saleh
FIDIC Construction Contract
The Red Book
Conditions of Contract for Constructionfor Building and Engineering Works Designed by the Employer.1stEdition 1999
For building or engineering Works of largerand more complexthanminor projects.The design ismade by the Employer (in house if hehas the capabilitiesand authorizedto do so) or on behalfof the Employer by design consulting engineer.
Oftenincludessomeelementsof Contractor-designedcivil, mechanical, electricaland/or construction works.
3.1 Current FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
29Tahseen Saleh
The Red Book
The procurement of construction works takes place according to a standard pattern of pre-feasibility & feasibility studies, conceptual design, final design.
Then the consultant prepares the tender documents
The Employer or the consultant (on behalf of the Employer) announces for the tenders and either invites a specific list of contractors (short list), a specific category or grade of contractors or qualify (pre-qualification or post qualification) the contractors to participate if the project and the works are of special nature, higher requirements or more complicated.
The award is made to the most suitable bid (normally the lowest if the contractors have already been qualified).
3.1 Current FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
30Tahseen Saleh
The Red Book
Payment to the contractor is made by measurement of the completed works at the end of each month. Under the usual arrangements for this type of Contract the Employer:Provides finance
Appoints a consulting engineer to carry out the design work and prepare the tender documents.Appoints the Engineer to supervise the works and monitor the construction, administer the contract, certify payments, make determinations on issues raised by the parties, etc.
The Engineer may initiate variations.
The Employer wishes to be fully informed
Payments to the Contractor will be according to a Bill of Quantities or lump sum for the approved works.
The Employer seeks to ensure a fair sharing of the construction risks.3.1 Current FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
31Tahseen Saleh
FIDIC Plant and Design Build
The Yellow Book
Conditions of Contract for Plant and Design Build for electrical and mechanical plant and for building works, designed by the Contractor.
1stEdition in 1999
For projects of larger and more complex than minor works projects.The Employer may carry out some designs.
3.1 Current FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
32Tahseen Saleh
The Yellow Book
a) Electrical and mechanical Plant designed by theContractor
Traditional plant projects involve design,
manufacturer, delivery, erection, testing, etc. of plant by a contractor to an outline, certain requirements and performance prepared by theEmployer.
The Procurement of the supply and installation of
plant and equipment closely follow the same procedure of the Construction works.3.1 Current FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
33Tahseen Saleh
The Yellow Book
Some of the differences are:
Detailed design of the plant is the Contractor's responsibility;Most of the plant is manufactured off-site;
Contractor is associated with the a plant manufacturer or supplier or with civil works contractor.Payment is mainly made on a schedule of payments or based on the achieved progress of work of predefined milestones;
testing and commissioning are comprehensive and stringent;Procurement process may be in two stages of tendering which allows contractors / suppliers more chance to offer their own solutions to the Employer's Requirements
3.1 Current FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
34Tahseen Saleh
The Yellow Book
b) Building and Engineering works designed by the ContractorDesign-Build: design is mainly carried out by the
Contractor, who is responsible for the design and
the completed works which shall fit for purpose.The Employer provides the Employer's
Requirements and the Contractors designs and
builds the facility.The tender documents usually include drawings
showing the conceptual or preliminary design.The Procurement may be single or two stages.
3.1 Current FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
35Tahseen Saleh
The Yellow Book
Under the usual arrangements for this type of Contract (Plant and Design Build) the Employer:Provides finance
Appoints Engineer to administer Contract, monitor the design and manufacturing, installation and erection on site and construction. Also, certify payments, make determinations on issues raised by the parties, etc.
The Engineer may initiate variations.
The Employer wishes to be fully informed.
Payments to the Contractor will be according to achieved milestones or as per defined schedule of payments.
Contract is generally lump sum
The Employer seeks to ensure an equitable sharing of the construction risks and accepts the overruns may occur to contract sum and possibly the completion date.
3.1 Current FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
36Tahseen Saleh
FIDIC EPC/Turnkey Projects
The Silver Book
Conditions of Contract for EPC/Turnkey Projects.
1stEdition in 1999.
For different sizes and complexity of projects.
The Contractor fully designsand provides in accordance with the Employer's Requirements for the required works.
The Employer is not interfering with the designs.
3.1 Current FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
37Tahseen Saleh
The Silver Book
The need for contract forms where the emphasis is on a fixed final price and duration was the basis to publish the EPC/Turnkey form.
In addition, Owners (Employers) who do not have their own technical staff capable of designing the facility or who do not want to take the responsibility of design and / or in the absence of the required engineering experience of that specific field, Owners may go directly to qualified and capable contractors to carry out all the works.
It is believed that the overall implementation time can be less than that of traditional approach.Turnkey projects range from those with minimum requirements by the Employer to very detailed and complex requirements.
3.1 Current FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
38Tahseen Saleh
The Silver Book
Under the usual arrangements for this type of Contract the Employer:Provides finance.
Does not wish to be fully informed.
Wants the Contractor to be fully responsible for the design and construction of the project. Wants high degree of certainty that the contract price and the duration will not be exceeded. Is conveying the risks to the Contractor. Accordingly, he expects and is willing to pay more.Payments to the Contractor will be according to achieved milestones or as per defined schedule of payments.
Contract is generally lump sum.
3.1 Current FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
39Tahseen Saleh
FIDIC Design, Build and Operate Projects
The Gold Book
Conditions of Contract for Design, Build and Operate Projects.1stEdition in 2008.
For different sizes and complexity of projects.
The project is long-term and it combines the operation and maintenance into one contract with the design and building of the facility.
3.1 Current FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
40Tahseen Saleh
The Gold Book
The Contractor will usually be a joint venture or consortium.The Contractor will be responsible for providing a lasting service through good quality and reduced maintenance and operation costs.
The Employer is responsible for financing the project.New procedures and new terminology are introduced in the Gold book which are not found in the other FIDIC books.
3.1 Current FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
41Tahseen Saleh
FIDIC Construction (Pink)The Pink Book
Conditions of Contract for ConstructionMDB Harmonized edition, for Building and Engineering Works Designed by the Employer.
1stEdition 2005 and was amended in 2006 and 2010.
This is a variant of the 1999 Red Book for use on projects that are funded by certain Multilateral Development Banks (MDBs).
3.1 Current FIDIC Contracts
FIDIC ʹINTERNATIONAL FEDERATION OF CONSULTING ENGINEERS ʹWWW.FIDIC.ORG ʹFIDIC@FIDIC.ORG ʹ© 2020
42Tahseen Saleh
FIDIC Conditions of Contract for Underground WorksThe Emerald Book
Conditions of Contract for Underground Works.
quotesdbs_dbs7.pdfusesText_13[PDF] fiesta 1980 pdf
[PDF] fight bac video
[PDF] fight bac word find
[PDF] fight for love 3 pdf
[PDF] fight for love racer pdf
[PDF] fight for love tome 2 pdf
[PDF] figure de style 3eme
[PDF] figure de style bac
[PDF] figure de style definition
[PDF] figure de style en francais
[PDF] figure de style exemple
[PDF] figure de style exercice
[PDF] figure de style liste
[PDF] figure de style pdf bac