Reasons for Charles de Gaulle Airport Collapse
9 авг. 2017 г. External tensile reinforcement shown in Fig. 4. (Point 2)
GRENZGÄNGER – VOM UMGANG MIT LEICHTEN
Roof collapse of the terminal 2E at Paris-Roissy Charles de Gaulle Airport Charles de Gaulle airport collapse causing the death of 4 people. Design by ...
Progressive Collapse Design and Analysis of Space Structures
3 мар. 2016 г. ening of the roof. The cracks were formed due to high stress caused in. FIGURE 3.3 Partial collapse of Charles de Gaulle Airport Terminal 2E.
Forensic engineering and collapse databases
& the Auguste Perret Meteor tunnel collapse in Paris
AÉROPORTS DE PARIS MANAGEMENT REPORT 2018
30 июл. 2018 г. Groupe ADP carries out the principal businesses in the airport value chain – financing designing and operating infrastructure –.
CSR REPORT
2 дек. 2019 г. Causing a collapse in air traffic this global health crisis now ... CDG: Paris-Charles de Gaulle Airport. CDM: Collaborative Decision ...
DOCUMENT DE REFERENCE
31 дек. 2006 г. For example the collapse at terminal CDG 2E at Paris - Charles de Gaulle airport resulted in the ... roof of terminal CDG 1 at Paris - Charles ...
Page numbers in italics refer to figures. Page numbers followed by a
Algo Centre Mall roof collapse (Elliot Lake. Canada)
Annual Report - 2022 - 2023
15 сент. 2023 г. Recently we have also announced a brand-new year-round route to Paris. Charles de Gaulle Airport with easyJet ... roof of the airport's terminal ...
Aéroports de Paris S
lot located on the roof of terminal CDG 1 at Paris - Charles de Gaulle to increase • Reconstruction of the CDG 2E boarding area following the collapse of a ...
Reasons for Charles de Gaulle Airport Collapse
9 août 2017 Key words: Charles de Gaulle airport collapse structural failure
GRENZGÄNGER – VOM UMGANG MIT LEICHTEN
Roof collapse of the terminal 2E at Paris-Roissy Charles de Gaulle Airport Charles de Gaulle airport collapse causing the death of 4 people.
Forensic engineering and collapse databases
include. & the Auguste Perret Meteor tunnel collapse in Paris
Effondrement et reconstruction du Terminal 2E de laéroport Roissy
1 mars 2021 L'aéroport Roissy-Charles de Gaulle a été inauguré en 1974 ... [13]: Reasons for Charles de Gaulle Airport Collapse
Swiss Re Global Engineering
(US) Hyatt Regency Hotel collapsed causing In May 2004 the roof of Terminal 2E at Paris'. Charles de Gaulle airport partially collapsed.
DOCUMENT DE REFERENCE
1 janv. 2022 For example the collapse at terminal CDG 2E at Paris - Charles de Gaulle airport resulted in the temporary closure of the terminal and ...
Case Study: The New Terminal 2E at Paris – Charles De Gaulle
built concrete + external metal structure) of the roof structure of the boarding area in terminal 2E at CDG Airport collapsed for yet unknown reasons
Reliability study and simulation of the progressive collapse of Roissy
24 mars 2015 Paris Charles de Gaulle Airport also known as Roissy Airport is the ... but rather a number of causes for the collapse in a design that had.
CPWR
including a roof collapse. protection equipment that was secured to the roof of the structure. ... out causing the roof to collapse. All three.
Structural Analysis and Design to Prevent Disproportionate Collapse
3 mars 2016 ening of the roof. The cracks were formed due to high stress caused in. FIGURE 3.3 Partial collapse of Charles de Gaulle Airport Terminal 2E ...
Case Studies in Engineering Failure Analysis - ????????
collapse Failure Sensitivity A B S T R A C T Paris Charles de Gaulle Airport also known as Roissy Airport is the world’s eighth-busiest airport in passengersserved InMay2004 thenews ofcollapse ofaportionofTerminal2E leaving four casualties shook the world Luckily no boarding had been taking place in the collapsed
When buildings fail: ethics for the worst-case scenario
2004 roof collapse at Charles de Gaulle Airport only because it occurred in early morning It is still anguishing to contemplate the chaos vast destruction and massive loss of life that would have resulted had the potential collapse of the 59-story Citicorp Tower in midtown Manhattan not been averted during the summer of 1978
PRECAST DOUBLE TEE ROOF COLLAPSE INVESTIGATION - A CASE STUDY
likely restricted flow into the roof drains CAUSE OF COLLAPSE It did not take long to determine that the collapse was caused by the severe rainfall and that the covered-up overflow scupper limited roof slope new roof membrane hail accumulation and ill-maintained drains were all contributing factors to the collapse The rainfall runoff
FALLS FROM ROOFS RISKS AND PREVENTION - CPWR
Factors that contribute to falls from roofs include unprotected roof edges unguarded roof openings such as skylights roof collapses and leading edges Without fall protection these falls can result in serious injury or death 4 In fact the absence of fall protection is the most frequently cited workplace violation by the Occupational Safety
Searches related to paris airport roof collapse cause filetype:pdf
AIRPORT ROOF REPAIR Project No 2021-0385 I PROJECT DESCRIPTION Work to be performed shall include furnishing all labor services materials insurance labor and equipment to provide and install the South Bend Airport Roof Repair project including but not limited to parapet cap/coping remove existing roof replace damaged substrate and roof
What happened at Charles de Gaulle Airport in Paris?
- Protesters blockaded train stations, Charles de Gaulle Airport in Paris and refineries. High-speed and regional trains, the Paris metro and public transportation systems in other major cities were disrupted. About 30% of flights at Paris Orly Airport were canceled. The Eiffel Tower and the Versailles Palace were closed Thursday due to the strikes.
What happened to the Paris skyscrapers?
- While low-rise Paris remained pristine, skyscrapers were sent to La Defense, a futuristic suburb just beyond the Arc de Triomphe. The first plan appeared in 1964 and was criticized for being dull; the second plan put forward much higher and more dramatic buildings and was approved in 1968.
What happened to Istanbul Airport roof collapse?
- The closure of Istanbul Airport where the roof of one of the cargo terminals collapsed under heavy snow, causing no injuries -- grounded flights stretching from the Middle East and Africa to Europe and Asia.
What's happening at Paris's airport?
- STORY: A strike at Paris’s main airport on Thursday (June 9) is adding to a summer of chaos for European travellers. Workers at Charles de Gaulle are demanding more pay. A quarter of all flights from the airport are cancelled. "Flights are picking up and we didn't expect it to happen so fast.
Roissy
Charles de Gaulle Airport
Y. El Kamari
a , W. Raphael a, *, A. Chateauneuf b,c aEcole Supe´rieure d"Inge´nieurs de Beyrouth (ESIB), Universite´Saint-Joseph, CST Mar Roukos, PO Box 11-514, Riad El Solh Beirut 1107 2050,
Lebanon
b Universite´Blaise Pascal, Institut Pascal, BP 10448, F-63000 Clermont Ferrand, France c LGC/CUST - UBP, Campus des Ce´zeaux, 63174 Aubie`re, France1. Introduction
Terminal
2E, with a daring design and wide open spaces, was Charles de Gaulle Airport"s newest addition. Terminal 2E had
been inaugurated in 2003 after some delays in construction. On the 23rd ofMay 2004, not long after its inauguration, a part
ofTerminal 2E"s ceiling collapsed early in the day, leaving four casualties. Some questioned the construction methods as
beingthe primary cause, which were rushed as the project was a month behind schedule due to technical problems, and
somehave also considered the possibility of improper design as the cause of the accident. In the following, a deterministic
analysisand a mechanical reliability assessment will be elaborated. We will show the importance of reliability assessment
and long term strains of materials, especially for public constructions where the human and economic repercussions are
heavyto bear. The purpose of our research is to study the problem using the available data in order to examine the real
reasonsof the incident, to see if it were possible to predict the structure"s failure from the beginning and to simulate the
progressive collapse of the structure. 2.General overview of Roissy"s Terminal 2E [1]
We will first describe the terminal, its different construction phases, the incidents that occurred before the accident and thecollapse itself. Then we will present in a general way the principle of finite element modeling, recommendations for good
Case Studies in Engineering Failure Analysis 3 (2015) 88-95A R T I C L E I N F O
Article history:
Received 17 December 2014
Received in revised form 13 March 2015
Accepted 13 March 2015
Available online 24 March 2015
Keywords:
Finite
element modelingReliability
Progressive
collapseFailure
Sensitivity
A B S T R A C T
Paris Charles de Gaulle Airport also known as Roissy Airport is the world"s eighth-busiest airport in passengers served. In May 2004, the news of collapse of a portion of Terminal 2E leaving four casualties shook the world. Luckily, no boarding had been taking place in the collapsed area which consisted of a boarding area and three footbridges. This part of the terminal had an innovative design consisting of a vaulted concrete tube. We chose to model a representative part of the terminal to observe the structure"s behavior. The purpose of our research is to explain the structure"s collapse and to see if there were deficiencies from the design phase. Also, our new fine-grained model using Ansys Software makes it possible to explain the progressive collapse of the structure, which was the main challenge of our study. Moreover, a sensitivity analysis was performed in order to study the importance of each of the variables taken into account in the model.2015 The Authors. Published by Elsevier Ltd. This is an open access article under the CC
BY-NC-ND
license (http://creativecommons.org/licenses/by-nc-nd/4.0/). * Corresponding author. Tel.: +961 1 421354; fax: +961 4 532645.Contents lists available at ScienceDirect
Case Studies in Engineering Failure Analysis
jou r nal h o mep age: w ww.els evier .co m/lo c ate/c sef a2213-2902/?
2015 The Authors. Published by Elsevier Ltd. This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/
licenses/by-nc-nd/4.0/).modeling and problems encountered during the process. We will also talk briefly about the behavior of concrete (creep,
shrinkage). 2.1.Description of the terminal
Terminal
2E consists of three parts: the main building, the boarding area and the isthmus that connects the two buildings.
Theboarding area is formed by a succession of ten shells giving access to aircrafts through nine gateways (Fig. 1).
The650 m long terminal is made up of a series of 4 m wide panels adjacently connected, forming a deformed tube which
restson parallel longitudinal beams. Structurally it acts as a form of an extreme portal frame. There is a 30 cm thick precast
concreteshell and a steel external tension truss, with simple vertical struts connecting the elements. The tube is surrounded
bya glazed roof which feeds light into the structure through square voids cast into the shell (Fig. 2). Three walkways are cut
intothe structure (it was at one of these points that the structure failed). These footbridges link the boarding area to the
central area of the terminal. 2.2.Construction of the terminal
Afull-scale prototype consisting of two common arcs (total height of 18 m, maximum opening of 31 m) based on four
columnswas achieved. But it is interesting to note here that the prototype did not allow testing the behavior of the extremity
zonesof the shells or the behavior of beams. It should be also noted that it is after the striking that the shell takes in its own
weight.The striking was accompanied by an instantaneous deformation of 10 cm vertically while the design had predicted
2.8cm. These deformations continued later on with time. This observation lets us imagine the consequences in the case of
striking of asymmetrical arcs where the footbridges are located. 2.3.Incidents before the collapse
Between
the beginning of the construction phase and the date of the collapse, many incidents took place: right after
installingthe first rings, cracks were seen in the columns. After the striking, we had instantaneous deformations and a
spreadingof the shell. This deformation continued over time because of the creep and shrinkage of the concrete. Cracks near
thefixation plates of the footbridges were observed in zones where the collapse occurred. These cracks have been attributed
tothe deformation of the shell, but without showing any undue concern. Transverse cracks appeared very quickly in the
midline (under the support line of struts) of all solid elements located at the extremity of the shells. 2.4.Collapse of the terminal
OnSunday May 23rd at 6:57, six arcs located in the boarding pier collapsed abruptly with a loud cracking noise (Fig. 3). A
policelieutenant who witnessed the collapse found around 6:45, a significant tear in the lateral wall of a concrete element of
asolid shell adjacent to the footbridge in the middle of the zone which later on collapsed. This tearing was reported about
5:30by a cleaning crew and it also seemed that there was concrete dust that fell before the accident. The following
Fig. 1. General view of the terminal.Y.
El Kamari et al. / Case Studies in Engineering Failure Analysis 3 (2015) 88-95 89observations of the collapsed area were made: on the southern side, arcs failed over and the shell was perforated by struts;
whereason the Northern side, some struts perforated and went through the shell however arcs stayed on the columns but
were fractured. 2.5.Potential causes
Theexperts pointed out that there was no single fault, but rather a number of causes for the collapse, in a design that had
littlemargin for safety. The inquiry found the concrete vaulted roof was not resilient enough and had been pierced by
metallicpillars and some openings weakened the structure. Sources close to the inquiry also disclosed that the whole
buildingchain had worked as close to the limits as possible, so as to reduce costs. Some people also denounced the building
companies for having not correctly prepared the concrete.Having
said that, it is necessary to model the collapsed part of the terminal to try to find the real causes of the collapse. For
this, we expose in the following the geometry and the model of the structure. 3.Modeling the terminal
Ina previous study, the terminal was modeled using ST1 software by a bar model that required 1558 nodes and 2320 bars.
[1].Fig. 2. Close view of the structure.
Fig. 3. Collapsed zone of the terminal 2E.Y.
El Kamari et al. / Case Studies in Engineering Failure Analysis 3 (2015) 88-9590As for our modeling of the concerned section, we used Ansys software and a shell model that required 10,488 shell
elements,12,978 nodes and 814 bars for struts and ties [2]. It has to be noted here that Ansys software allowed us to obtain a
fine-grainedmodel representing better the reality. The complexity of our structure has been considered: openings in the
shell,connection between the arcs by fragile corners iron, shortened arcs right on the gateways placement, and finally the
dissymmetryof the structure and the applied loads. This model using Ansys allowed us to properly take into consideration
bothwind and temperature loads. It also made it possible to represent the progressive collapse of the structure, which was
the main breakthrough of our study. Thelong term deformation of materials (creep, shrinkage, relaxation) have been taken into account in order to explain the
largedeformations of the rings which lead to the ruin of structure [3]. We will describe here-after our model, its geometry, its
characteristicsand its loads. We will study the results that it gives us and by doing so we will assess the deterministic part of
our research. 3.1.General description of the model
Wechose to model the first eight rings starting from the isthmus. By doing so, we took into account the openings of three
gatewaysand a common ring (Fig. 4). First of all, we generate the code for the first ring by creating the neutral axis" points on
thetheoretical outline. In the same way, we draw the second ring tangent to the first. We note that some rings are shortened
because of the footbridges. In that case, the neutral axis is cut. 3.2.Elements" characteristics
Theconcrete structure is stiffened by struts and ties. The struts and ties are modeled by bar elements. The bars forming
thestruts are biarticulated and connected to the rod and the ring with rigid elements. The anchoring of the tie rods in the
reinforcedarea is formed by a rigid element. As for the beams, they span the length of the designed area. They are connected
tothe tip nodes of the rings by rigid elements. Each line of beams rests on a row of columns (that are 8 m apart) by means of
bearingseach placed on the top of a pillar. The eight rings are linked to each other by transversal angle irons. These angle
irons hold the different arcs together. The mechanical characteristics we used for the materials are listed in Table 1: 3.3. Loads The loads are taken as following: ? The dead weight of the structure is computed by Ansys. ? The glazed roof weight is considered as a linear load which is based on the areas concerned.? The gateways weight is modeled by a vertical force Fz = ?120 kN in two points of attachment for each of the three
gateways.Fig. 4. Ansys model.
Table 1
Mechanical
characteristics of the elements.Concrete
Steel (tie rods and struts)
TypeB 40 f
c = 40 MPa Type S460 f y = 460 MPaYoung"s
modulus (long term) E v = 12.65 GPa Young"s modulus E = 210 GPaYoung"s
modulus (short term) E i = 37.95 GPaY. El Kamari et al. / Case Studies in Engineering Failure Analysis 3 (2015) 88-95 91 ? The wind load is calculated according to Eurocode.? The thermal gradient: since an extremely low temperature (?20 8C) was reached the night preceding the accident, we took
intoconsideration this unusual temperature. After applying thermodynamic calculations to the structure, we obtain a
thermal gradient ranging from 7 8C on the inside of the concrete shell to ?13 8C on the outside. 4.Comparison between different results
Theanalysis is first conducted on a short term, taking into consideration the permanent loads as well as the wind and the
thermalloads. The analysis is also done on the long term, taking into account the same loads as the previous analysis, as well
asthe long term effects of concrete (creep, shrinkage) [4]. For the short term, we have considered the short-term elastic
modulus E c = 37 GPa; while for the long-term, we have considered E c = 12 GPa. The results are presented in Table 2. Table3 represents several values of the deflection for different scenarios with a comparison to the previous results
obtained using ST1 software [1]. Wenotice first of all a high increase between short and long terms which exceeds 60%. The difference between both states
ishigher than values usually found in the literature [5]. Also, the obtained results using ST1 and Ansys software confirm the
valuesmeasured on site. This allows us to validate our model. We note a remarkable difference for both short and long term
deflectionsbetween predicted results and the ones measured on site. This proves that the simulation of the structure by the
designoffice was not very accurate. Finally, on the long term, the measured deflection as well as the one given by Ansys
exceeds the allowable value of 12.40 cm. 5.Progressive collapse
Inorder to explain the succession of the collapse"s incidents, we have simulated the collapse (dead weight, wind load,
thermalgradient, creep of concrete, etc. are taken into account). A punching of the shell by struts clearly explains the
phenomenaobserved by the witnesses and the condition of the shell after the collapse. We therefore compute the ultimate
resistanceto puncture and we notice that the efforts in the struts exceed the shell"s capacity of 1.43 MN which has been
calculatedtaking into account the presence of reinforcements and the effect of the compressed shell [1,6]. Fig. 5 shows us
wherethe maximal moment in the shell is located. At that point, the structure is weakened, the efforts in the struts exceed
the shell"s maximum resistance, and the shell is therefore punched. Asfor simulating the ''progressive"" collapse, we start by decreasing the modulus of elasticity of the punched area of the
shell. The decrease of Young"s modulus is justified by the following [14]: We know that: s = EeWe can also write: s = (1 ? D)Eewhere
Table 2
Deflection
values on the short and long terms, for ultimate limit state. Loads Short-term deflection (cm) Long-term deflection (cm) G Dead load ?7.47 ?12.20Glazed
roof weight ?1.36 ?2.23Gateways
weight ?0.146 ?0.368 TThermal
gradient ?0.705 ?0.539 W Wind1.02 1.81
ULSPG ?8.97 ?14.8 1.35G + 1.5T + 1.5 ? 0.6W ?12.20 ?19.20 1.35G + 1.5W + 1.5 ? 0.6T ?11.15 ?17.70Table 3
Deflection
values for different scenarios.Scenarios
Short term deflection (cm) Long term deflection (cm) Value given by our Ansys model 12.20 19.20 Value given by our ST1 model 11.74 18.58Measured
value on site 10.00 20.00 Value predicted by the design office 2.80 5.00Allowable
value 12.40 12.40Y. El Kamari et al. / Case Studies in Engineering Failure Analysis 3 (2015) 88-9592D = 0 if the material is intact;
D = 1 if the material is damaged. D being a damage parameter relative to the history of deformation. Fig.6 shows the new distribution of moments in the shell after decreasing the role of the punched elements of the shell
(by taking D = 0.50). Weproceed with the same strategy, minimizing Young"s modulus in the yielded parts of the structure in order to observe
thestructure"s behavior. Fig. 7 shows the new distribution of moments in the shell after nearly canceling the role of the
yielded elements (for D = 0.95). Atthe final state, the moment in the shell where the footbridges are located is greater than the one in the other side. The
momentexceeds by far the shell"s resistance. The structure failed with no doubt at this location. Indeed, we have a fail over of
shellelements from one side and a fracture of these elements on the other as we can see in the following pictures (Fig. 8).
6.Sensitivity analysis
Inprevious works [1,7], a reliability-based assessment of the structure was made in terms of deflection [8,9]. A
mechanical-reliability coupling was performed between the design software and Phimeca. Results gave us a reliability indexb of 1.824. Since an airport is considered to have a very serious financial impact, and since it endangers a large number of
Fig. 5. Initial bending moment distribution in the shell. Fig. 6. The new distribution of the moment in the shell for D = 0.50.Y. El Kamari et al. / Case Studies in Engineering Failure Analysis 3 (2015) 88-95 93persons, the obtained value is smaller than the allowable values for this kind of structures and we can fairly say that the
structure presented a deficiency from the beginning according to the previous reliability study. In the following, we have studied the sensitivities s i of each of the variables [10,11]. The sensitivity measures reflect the importanceof each random variable drawn from the direction cosines. So, the reliability of the structure is affected by all
these variables. The sensitivities are calculated as following: s i @b x i where b is the reliability index and x i is the mean value of the considered variable i. The sensitivities s i of each of the variables are given in Table 4 and represented in Fig. 9. Wenotice that the concrete compressive strength is by far the most sensitive variable. This means that a slight change or
insecuritythat could affect the concrete (design, mixing, casting. . .) would induce a large effect on the reliability of the
structure. This variable should necessarily be controlled by a quality control on the worksite.Fig. 7. Final distribution of moment in the shell after canceling the role of the yielded elements (D = 0.95).
Fig. 8. Condition of the shell after the collapse.Table 4
Sensitivities
of each of the variables. x i Sensitivity Numbers related to the cake slices in Fig. 9Materials
Concrete
f ckquotesdbs_dbs8.pdfusesText_14[PDF] paris apartments for rent long term furnished
[PDF] paris apartments rentals long term
[PDF] paris arrondissement 7 map
[PDF] paris arrondissement 7 population
[PDF] paris assas inscription master 2
[PDF] paris bank
[PDF] paris barcelona train times
[PDF] paris big red bus tour map
[PDF] paris bus pass
[PDF] paris cannes tgv prix
[PDF] paris capital of the nineteenth century benjamin
[PDF] paris capital of the nineteenth century summary
[PDF] paris cdg icao code
[PDF] paris central rental