[PDF] [PDF] GUIDE TO TRENCH EXCAVATIONS (SHORING SUPPORT AND

Trench excavations are carried out principally to allow installation or repair of public utilities, drains and sewers to serve populated areas The Geotechnical



Previous PDF Next PDF





[PDF] Excavations et tranchées

Excavation : partie de terrain creusée à une profondeur d'au moins 1,2 m (4 Maintenir toute excation ou tranché raisonnablement assécher (C S art 3 15 6)



[PDF] GUIDE TO TRENCH EXCAVATIONS (SHORING SUPPORT AND

Trench excavations are carried out principally to allow installation or repair of public utilities, drains and sewers to serve populated areas The Geotechnical



[PDF] Trenching and Excavation Safety - OSHA

Trench Safety Measures Trenches 5 feet (1 5 meters) deep or greater require a protective system unless the excavation is made entirely in stable rock If less 



[PDF] Trenching and Excavation Safety - OSHA

What is the difference between an excavation and a trench? OSHA defines an excavation as any man-made cut, cavity, trench, or depression in the Earth's 



[PDF] Excavation - Bruxelles Environnement

On réalise les excavations en talus, par tranches, en terrasses Au besoin des mesures de soutènement sont prises (blindage, palplanches, pieux, parois 



[PDF] Work safely in excavations and trenches - ILO

or material falling onto workers in the excavation or trench • Measures to prevent persons, materials or objects falling into the excavation or trench or the inrush 



[PDF] Accessoires innovateurs pour caissons de tranchée en acier

AMERICA'S TRENCH BOX BUILDER™ AMERICA'S dans l'excavation sur une pente de quatre le niveau du sol et le fond de l'excavation • Si on utilise un 



pdf Excavation de tranchées - IHSA

EXCAVATION DE TRANCHÉES Types de sol Le type de sol détermine la résistance et la stabilité de parois de la tranchée L'identification des types de sol exige des connaissances de la compétence et de l'expérience Même le sol dur peut contenir des failles en veines ou en couches qui le rendent instable lors de l'excavation



Pour mieux exécuter les travaux de creusement d’excavation

Planifier organiser contrôler : pour des chantiers sécuritaires Le but de ce document est d’aider les employeurs à planifier leurs activités de prévention sur les chantiers d’excavation et de tranchée pour assurer la sécurité sur ces chantiers

[PDF] Excavation de tranchées – inspection

[PDF] excavations in the necropolis of salamis - Patinage Artistique

[PDF] excavatrice-aspiratrice - Conception

[PDF] Excédents bagages Ryanair

[PDF] Exceed 8.0 Nouvelles fonctionnalités - La Technologie Informatique Et

[PDF] Exceed Freedom™ 2008

[PDF] Excel - Atelier - Automatiser vos tableaux avec les macro - Anciens Et Réunions

[PDF] Excel - Bruno Martin - Shareware Et Freeware

[PDF] EXCEL - ESCO Wesford

[PDF] Excel - initiation

[PDF] EXCEL - LITIS - Université du Havre - Anciens Et Réunions

[PDF] excel - mes fiches pratiques

[PDF] Excel - Perfectionnement - Anciens Et Réunions

[PDF] EXCEL - Sortieren von Listen und Filtern

[PDF] Excel 2000 Bases - Ordinateur

GUIDE TO TRENCH EXCAVATIONS

(SHORING SUPPORT AND DRAINAGE MEASURES)

Utilities Technical Liaison Committee

HIGHWAYS DEPARTMENT

and

Geotechnical Engineering Office

CIVIL ENGINEERING DEPARTMENT

THE GOVERNMENT OF THE HONG KONG

SPECIAL ADMINISTRATIVE REGION

February 2003

GUIDE TO TRENCH EXCAVATIONS

(SHORING SUPPORT AND DRAINAGE MEASURES)

Utilities Technical Liaison Committee

HIGHWAYS DEPARTMENT

and

Geotechnical Engineering Office

CIVIL ENGINEERING DEPARTMENT

THE GOVERNMENT OF THE HONG KONG

SPECIAL ADMINISTRATIVE REGION

February 2003

2

FOREWORD

Trench excavations are carried out principally to allow installation or repair of public utilities, drains and sewers to serve populated areas. The Geotechnical Engineering Office (GEO) of the Civil Engineering Department (CED) recently undertook a study on failures of trench excavations in Hong Kong. The study found that between 1986 and 2000, there were at least 10 deaths and 4 injuries caused by the failures of trench excavations. The study also found that a number of landslides resulting in significant social disruption in recent years were related to trench excavations adjacent to slopes. Therefore, the study concluded that the risk from trench excavations is not low and some improvement measures should be done to enhance the safety standards of trench excavations in Hong Kong. The findings of the study with recommendations on enhancement of the safety of trench excavations were presented to the Standing Committee on Slope Safety (SCOSS) of Environment, Transport & Works Bureau (ETWB). It was decided by the SCOSS that a Working Group should be formed under the Utilities Technical Liaison Committee (UTLC) of Highways Department to take the recommendations forward, including the preparation of a technical guide to trench excavations, and GEO/CED should provide technical assistance to the UTLC to prepare the guide. The Working Group, composed of the major utility undertakings, representatives from Hong Kong Construction Association, the Association of Consulting Engineers of Hong Kong, Highways Department, Water Supplies Department, Drainage Services Department and Labour Department, in conjunction with GEO/CED prepared this Guide on good practice of shoring support and drainage measures for trench excavations. As part of the Government's continuing effort to promote a safe and healthy working environment, it is the intention of this Guide that the safety of the personnel involved in the works and also the general public who may be affected by trench collapses or failures can be enhanced. (C. K. WONG)

Chairman

Utilities Technical Liaison Committee

Highways Department

February 2003

3

CONTENTS

Page No.

Title Page 1

FOREWORD 2

CONTENTS 3

1.0 INTRODUCTION 5

2.0 OBJECTIVE AND SCOPE 6

3.0 PLANNING STAGE 7

3.1 Desk Study 7

3.2 Timing and Location 7

3.3 Statutory Requirements 8

4.0 DESIGN STAGE 9

4.1 Temporary Support Design 9

4.2 Design Considerations 10

4.2.1 Loading 10

4.2.2 Drainage 10

4.2.3 Groundwater Control 11

4.2.4 Existing Man-Made Slope Features 11

5.0 CONSTRUCTION STAGE 12

5.1 Installation of Support 12

5.2 Special Drainage Provisions in the Wet Season 12

5.3 Backfilling of Trench and Reinstatement 13

5.4 Precaution in Use of Machinery 13

5.5 Other Considerations 14

4

6.0 SITE SUPERVISION AND SITE SAFETY INSPECTION 15

6.1 Site Supervision 15

6.2 Site Safety Inspection 16

6.3 Safety Checklist for Supervisors 16

6.3.1 Drainage Provisions 17

7.0 REFERENCES 19

APPENDIX A : TYPICAL ARRANGEMENT OF SHORING

DETAILS21

APPENDIX B: RECOMMENDED DRAINAGE MEASURES 34

5

1.0 INTRODUCTION

The Geotechnical Engineering Office (GEO) of the Civil Engineering Department (CED) recently carried out a study on failures of trench excavations in Hong Kong. The study included a review of known past failures of trench excavations, and also the current technical standards and statutory requirements for trench excavations. The study has revealed that, between 1986 and 2000, fifteen reported failures associated with trench excavations resulted in 10 deaths and 4 injuries. In a very serious single incident in 1966, a retaining wall collapsed killing 6 people and injuring 16 others. Trench excavation at the toe of the wall was found to be the main cause of the collapse. The study also found that a number of significant landslides in recent years, which resulted in injuries and serious social disruption, were related to trench excavations adjacent to slopes. The details and findings of the study are documented in the Special Project Report SPR

2/2001, GEO (2001).

The GEO/CED study concluded that the risk from trench excavations is not low. A Working Group was therefore formed under the Utilities Technical Liaison Committee (UTLC) of Highways Department to prepare guidelines to promote safe practice for trench excavations. This document presents the recommendations of the Working Group as part of the Government's continuing effort to promote a safe and healthy working environment for all personnel in construction sites and others who may be affected by the works. 6

2.0 OBJECTIVE AND SCOPE

Trench excavations are carried out principally to allow installation or repair of public utilities, drains and sewers to serve populated areas. The purpose of this Guide is to provide recommendations on good practice of shoring support and drainage measures for trench excavations in order to enhance the safety of the people who may be affected by the excavation works or their collapses. Before a trench is excavated, the designer should bear in mind that the trench support system and associated precautionary measures should be required to serve two purposes: (i) stability of the trench itself, and (ii) avoidance of any adverse effect on the stability of adjacent slopes and in turn the safety of the public. ("Slopes" in this Guide should be taken to mean man-made slopes, retaining walls or sloping natural ground.) As determined by the GEO/CED study (GEO, 2001), the collapse of trenches is attributed to inadequate shoring, largely due to non-compliance with contract specifications and statutory requirements. However, one of the major contributory factors in the case of trench-related slope failures was found to be inadequate drainage provisions. In view of the above, this Guide emphasizes the deficiencies identified by the GEO/CED study, i.e. the need for adequate shoring support and drainage measures, and the need to comply strictly with site supervision requirements and site safety inspections. Therefore, the users of this Guide should refer to the relevant documents on other aspects related to the construction safety of trench excavation which are not covered (e.g. confined spaces, electricity supply lines protection, gas safety, site traffic management, etc.). It must also be stressed that the guidelines given in this Guide are in no way exhaustive, and professional judgement must be exercised in all cases. The Guide is intended to be used by all personnel who are involved in the planning, design, construction and supervision of trench excavation works, including contractors, utility companies, consultants, government departments and any other parties concerned. 7

3.0 PLANNING STAGE

3.1 Desk Study

When a trench excavation is being planned for any purpose, a thorough search should be made for information about any existing utilities adjacent to or crossing the line of the planned trench, including their sizes, locations and alignments. Most of the underground utilities are live systems, such as electricity, water, sewer and gas, and can be dangerous to workers when damaged or fractured. Particularly for gas, water mains and sewage rising mains, ground movement resulting from excavation may be sufficient to cause these mains to fracture. If the planned trench is located near slopes, special attention should be paid to the presence of any pressurized water mains as any damage to the pipes could lead to slope failures. It is important to search the Slope Information System via the Hong Kong Slope Safety website (http://hkss.ced.gov.hk) to identify any relevant slope information, such as past instability, substandard slopes with outstanding Dangerous Hillside Orders and slopes under the Landslip Preventive Measures Programme. Water Supplies Department (WSD) in their publication on "Guidelines for Excavation near Water Mains" (WSD,

2000) sets out procedures and practices for safe working near water mains. In addition,

as required under HyD's "Conditions of Permit", utility companies should be consulted for locations of their existing installations in the vicinity of the planned trench prior to commencement of excavation. Other site conditions should also be assessed. They include traffic loads, vibration of construction plant, condition and stability of adjacent structures, visible evidence of slope instability, groundwater table, any need for special excavation techniques such as dewatering, possibility of flooding by surface run-off, and flooding conditions in the vicinity of the site, etc. Detailed information on flooding blackspots in Hong Kong can be viewed via the Drainage Services Department (DSD) homepage (www.info.gov.hk/dsd). The permit holders, designers and contractors should familiarize themselves with the relevant Ordinances, Regulations, Codes of Practice and Guides before opening up a trench. A list of useful references is provided in Sections 7.1 and 7.2.

3.2 Timing and Location

Trench excavations without proper drainage provisions that are carried out adjacent to slopes can cause landslides in heavy rain. The Geotechnical Manual for Slopes (GEO, 1984) advises that "... trenches at the slope crests should not be opened up during the wet season unless unavoidable. If such trenches are to be excavated during the wet season, the trench should be protected against the ingress of runoff from the surface in which the trench is excavated...". The required drainage protective measures are discussed in Sections 4.2.2 and 5.2 below. 8 If the trench excavation is for new utilities, the routing of the utilities should be kept as far away from the crest or toe of a man-made slope as possible. As a general rule, water-carrying buried services should not be placed in a slope nearer to the crest of the slope than a horizontal distance equal to its vertical height. If it is unavoidable to lay water carrying services in the slope crest, measures to minimise possible adverse effects on slope stability given in Section 7 of the Code of Practice on Inspection & Maintenance of Water Carrying Services Affecting Slopes (WB, 1996) should be followed. It is also not desirable to have the whole length of a long trench opened up at any one time, even with support. Excavations should be in sections of shortest practical length, preferably not more than 100 m long. For sites perceived to be of high risk of flooding or landslide, an emergency plan is required; this may consist of contact telephone numbers and some emergency procedures such as fencing off potentially hazardous areas and provision for pumping out water from trenches. Site staff and full-time workmen, if available, should be made aware of and have access to the emergency plan.

3.3 Statutory Requirements

In accordance with the Land (Miscellaneous Provisions) Ordinance (LMPO), a person shall obtain an excavation permit issued under section 8 of the LMPO in order to make or maintain any excavation in unleased land. Unleased land includes all public roads and pedestrian pavements. Director of Highways is delegated with the power to issue excavation permits for excavations in streets maintained by the Highways Department. For excavations carried out in unleased land other than streets maintained by the Highways Department, Director of Lands is the Authority for issuing the excavation permits.quotesdbs_dbs17.pdfusesText_23