IPMA Level D: Certified Project Management Associate
This syllabus provides the details of the learning outcomes and assessment criteria for the IPMA Level D: Certified Project Management Associate qualification Both the learning outcomes and assessment criteria are aligned to the IPMA Individual Competence Baseline (ICB4) document, but the presentation of the content better reflects teaching
IPMA Level D: Certified Project Management Associate
This syllabus provides the details of the learning outcomes and assessment criteria for the IPMA Level D: Certified Project Management Associate qualification Both the learning outcomes and assessment criteria are aligned to the IPMA Individual Competence Baseline (ICB4) document, but the presentation of the content better reflects teaching
IPMA Level D guidelines SPM v9 - Institute of Project
Management and the resulting award of the certificate IPMA Level D – Certified Project Management Associate The certification process requires the candidate to demonstrate that they have the necessary know-how The certificate is valid for a period of 5 years 2 ADMISSION TO THE CERTIFICATION 2 1 ROLE DESCRIPTION AND ADMISSION CRITERIA
Indian Member of Globally Recognized
IPMA Level D® Certification (Certified Project Management Associate) IPMA Certification — recognized Globally Based on IPMA International Certification Regulations (ICR4) & IPMA Individual Competence Baseline (ICB4) Competence Elements Covered in Programme 1 Strategy 2 Governance, structures and processes 3 Compliance 4 Power and
Certified Project Management Associate IPMA Level D (Test
VZPM IPMA Level D Examinations Page 1 of 11 Certified Project Management Associate IPMA Level D® (Test-)Text-based tasks with answers Notes Please check whether this exam is complete and includes all pages from 1 to 11 Guideline time for this section of the exam 60 minutes The recommended time for each task is shown
Certified Project Management Associate IPMA Level D (Test
VZPM Prüfungen IPMA Ebene D Page 1 of 13 Certified Project Management Associate IPMA Level D® (Test-)Essay questions with answers Note Please make sure that you have the complete exam paper comprising pages 1 to 13 Time available for this part of the examination 60 minutes Recommended time per question is specified
Certification Regulations Certified Project Management
Experience in the project management competence elements is not compulsory at this level; but it is an advantage if candidates have previously applied their project management knowledge to some extent 4 Registration requirements To register for certification at IPMA Level D applicants must have, at least a bachelor’s degree,
IPMA Project Management Certificates
IPMA Level D, applicant´s instructions (03/2014 NCRG 3 1) 6 IPMA Level D - Certified Project Management Associate Certified Project Management Associate is an internationally recognised entry-level qualification in the area of project management The certificate is valid for five years The certification process is illustrated below
IPMA vottaðir verkefnastjórar D stig IPMA level D Certified
IPMA vottaðir verkefnastjórar D stig IPMA level D _ Certified Project Management Associate Stig Nafn Kennitala nr Vottun Gildistími D Adolf Þ Andersen 250982-4889 D-1288 6 4 2016 6 4 2021 D Aðalbjörn Hannesson 070489-3259 D-2029 22 10 2020 21 10 2025 D Aðalheiður Arna Rafnsdóttir 130862-3819 D-1768 8 4 2019 7 4 2024
Certified Project Manager Ipma Level D Test Multiple
Access Free Certified Project Manager Ipma Level D Test Multipleknowledge about managing projects You have shown to know the competences as described by the IPMA International Competence Baseline®, and have shown to know how to apply them Certified Project Management Associate (Level D) - IPMA
[PDF] SERVICE PUBLIC FÉDÉRAL SÉCURITÉ SOCIALE. Direction générale Politique sociale Domaine Réglementation. Allocations familiales. Circ.
[PDF] Inspection Pédagogique Régionale EPS. Lettre de rentrée 2016
[PDF] FORMATIONS OFFERTES AUX ELEVES DE TROISIEME DANS LA VOIE PROFESSIONNELLE AU SEIN DES EPLE ANNEE 2014-2015. Classement par bassin et par diplôme
[PDF] Mini conférence conviviale : TRAVAIL et VIH
[PDF] Descriptif des Unités d Enseignement Semestre 1 du parcours PLP Anglais/Lettres du master MEEF 2 nd degré
[PDF] SOUS-SECTION 2 RÉGIME D'IMPOSITION DES TITRES À REVENU FIXE DÉTENUS PAR LES ÉTABLISSEMENTS DE CRÉDIT ET LES ENTREPRISES D'INVESTISSEMENT [DB
[PDF] Colloque «Nous vieillirons ensemble» 22 et 23 octobre 2015 8h30-16h30 Auditorium de l AWIPH Montignies - Sur - Sambre
[PDF] Compte-rendu de la Réunion CMRR Du 21 Octobre 2004 Les présentations des intervenants sont disponibles sur le site : www.cmrr.vermeil.
[PDF] DIPLÔME DE COMPTABILITE ET DE GESTION
[PDF] FORMATION DEPARTEMENTALE DES AVS Adaptation à l emploi. 1ère journée L aide humaine pour l accompagnement des élèves en situation de handicap
[PDF] SOUTIEN AUX PROJETS COLLABORATIFS DE RECHERCHE ET DEVELOPPEMENT DES POLES DE COMPETITIVITE FONDS UNIQUE INTERMINISTERIEL REGIONS
[PDF]
[PDF] APPEL A PROJETS : «Gestion durable des eaux de pluie dans les projets d aménagements urbains» CAHIER DES CHARGES
[PDF] SCIENCES PO BORDEAUX. Réunion de rentrée 2015 Quatrième année
VZPM Prüfungen IPMA Ebene D Page 1 of 13 Certified Project Management Associate IPMA Level D® (Test-)Essay questions with answers Note Please make sure that you have the complete exam paper comprising pages 1 to 13 Time available for this part of the examination 60 minutes
Recommended time per question is specified
Number of questions: 9 questions
Maximum score 90 marks
The achievable number of marks per question is
specifiedAdmissible resources open books
Scoring in MC questions and essay questions (EQ)
Competence sections
Essay questions Marks achieved
Technical competence 50
Behavioural competence 20
Contextual competence 20
Total 90
Note: For the sake of convenience, all examination questions refer to the male gender. Date of issue: 30.01.2012 Version: M3-2012 Last revised: 30 Aug. 2012IPMA Examination Level D
Essay questions
VZPM Prüfung IPMA Level D VZPM_PMLD_TA_PRmA_M5-2012_EN Page 2 of 13PM Technical competences
P05 Stakeholders A51 1.02
Recommended time: 10 minutes for A51 12 points
Marks achieved
A51 Where possible, project environment analysis is carried out at the beginning of the project. In the context of this analysis, a wide range of information is collected that will serve as the basis of a specific project marketing concept. Since in many cases the required information is not easily accessible, project environment analysis will be repeated in the course of the project. Project environment analysis is carried out in four steps: a)Identification of stakeholders
b) Assessment of stakeholder needs c) Influence/interest analysis d) Analysis of stakeholder relations Question re. a): Consider possible stakeholders in terms of technical, financial and organisational considerations. Task List one possible project stakeholder for each of the dimensions (technical, financial, organisational).Answer to question a)
Dimension Possible stakeholder Max. 3 marks
Technical · Principal
· Customers
· Specialists
· Users
· Experts
1Financial · Principal
· Steering committee/decision-makers
· Sponsor
1Organisational · Project team
· Management
· Staff
· Users
1IPMA Examination Level D
Essay questions
VZPM Prüfung IPMA Level D VZPM_PMLD_TA_PRmA_M5-2012_EN Page 3 of 13 Question re. b): Having talked to the steering committee, the principal and one user, you notice that the expectations of these three stakeholders diverge significantly. They will be satisfied if .... Task State two expectations per stakeholder that express the stakeholder's satisfaction.Answer to question c):
Stakeholder is satisfied if .... Max. 6
marksSteering
committee · the formulation of the project assignment is clear and comprehensive · the project assignment coincides with the committee's agenda· an effective project team is involved
· cost and time schedules are adhered to
· the project manager is on top of things
2 Principal · project manager and project team are quick to recognize needs and problems · clearly differentiated solutions will be submitted · the principal feels that the direction is right and the user is satisfied · there is little resistance fro the user's side and the solution does not have to be forced through 2 User · the user acknowledges the advantages and expedient benefits arising to himself· his needs and fears are taken seriously
· the solution fits into his agenda
· many of his ideas have been integrated into the solution · it is made clear why certain aspects cannot be implemented · the project leads to added benefits for the user · the user is involved in the project's success· no additional costs arise in the longer term
2IPMA Examination Level D
Essay questions
VZPM Prüfung IPMA Level D VZPM_PMLD_TA_PRmA_M5-2012_EN Page 4 of 13 Question re. c) The influence and interests of the individual stakeholders are of particular relevance to project marketing. Influence / interest analysis relates to stakeholders' influence and interests in terms of the project. An example of an influence-interest matrix is presented below.Influence
high BKeep satisfied
ACooperate
low DNo specific activities
CKeep informed
Interest
low high Task (1)Which field contains the main stakeholders?
(2) What aspects should be taken into consideration for each of the main stakeholders? State at least
one form of integration. (3) State one representative of this group.Answer to question c):
(1) A Cooperate (2) They must be included in the planning and decision-making process. A detailed insight into the project and some form of involvement is required.(3) Representatives of this group consist of direct superiors, colleagues, active customers or suppliers.